Turnover of Projects to Power Operations
Report Information
Recommendations
We recommend the Senior Vice President, PO, evaluate projects returned to service where RTO has not been signed to determine if the equipment can be operated safely and reliably.
We recommend the Senior Vice President, PO, implement time frames for completion of the DCN process.
We recommend the Senior Vice President, PO, address issues identified that delayed completion of DCNs, including (1) vendors providing inaccurate drawings or not providing drawings timely, (2) TVA corporate groups not updating related drawings and UNID labels timely, (3) the DCN process being bypassed, and (4) project personnel not collaborating to identify and incorporate spare part or preventive maintenance changes timely, and implement any lessons learned for ongoing and future projects.
We recommend the Senior Vice President, PO, reinforce the requirement for RTO approval by plant management to ensure it occurs before the equipment is returned to service.
We recommend the Senior Vice President, PO, communicate expectations for turnover and ensure alignment between GP and PO personnel.