Sequoyah Nuclear Plant Vendor Selection Process
Report Information
Recommendations
We recommend the Director, Sequoyah Nuclear Plant Site Projects, ensure project managers request implementation estimates be developed as required by Nuclear Power Group Standard Programs and Processes 19.6.
We recommend the Director, Nuclear Supply Chain, ensure all bid evaluation concerns are addressed prior to awarding project work.
We recommend the Director, Nuclear Supply Chain, ensure the contracting officer provides effective oversight to technical teams by (1) requiring scoring criteria for each technical category and (2) making sure scoring is only based on categories that are included in request for proposals.