Sequoyah Nuclear Plant Moisture Separator Reheater Project
Report Information
Recommendations
We recommend the Vice President, Projects and Outages, develop a process for identifying and evaluating key assumptions of, and risks to, nonroutine projects prior to approval.
We recommend the Vice President, Projects and Outages, determine if additional steps are needed for estimates related to nuclear projects.
We recommend the Vice President, Projects and Outages, determine if the approximate $2.8 million in charges by the installation vendor were authorized.
We recommend the Vice President, Supply Chain, recover the $742,000 for unauthorized pipe fitters and any of the $2.8 million determined by Nuclear to be unauthorized.
We recommend the Senior Vice President and Chief Nuclear Officer, implement a verification process to ensure an engineering review is performed prior to placing orders for long-lead nuclear procurements.