Welding Services for Fossil & Hydro Projects
We audited $12.4 million of costs billed to TVA by a contractor for performing welding services for fossil and hydro projects. In summary, we found TVA had been overbilled $539,194 for (1) labor costs due to unsupported records and the contractor's use of incorrect labor rates; (2) mobilization, travel, and per diem costs that were ineligible or billed at incorrect rates; (3) duplicate costs and invoice calculation errors; (4) equipment costs due to the contractor's use of incorrect billing rates; and (5) unsupported costs.