All Reports

Succession Planning

Report Number
2006-513I

We conducted a review to determine what TVA has done to address challenges arising from TVA's aging workforce, retirements, and the resulting knowledge loss. Challenges facing power utilities as a result of the aging workforce include the loss of critical knowledge, the inability to find replacements with utility-specific skills, and the lack of bench strength within the organization. We determined TVA has adopted an Integrated Staffing Plan Principle, as well as several initiatives to support this principle which address the challenges arising from TVA's aging workforce.

Audit

OPM's Guidance for Addressing the Potential H5N1 Virus Pandemic

Report Number
2006-531I

We reviewed the Office of Personnel Management (OPM) guidance/requirements regarding a potential influenza pandemic to determine if TVA is in compliance with OPM requirements and/or has taken other proactive solutions. We found that OPM has issued some guidance for Federal agencies to follow in the event of a pandemic; however none are mandatory for agencies to implement. TVA is currently reviewing OPM guidance and has taken other proactive actions by adopting and adapting the Nuclear Energy Institute guidelines.

Audit

Retroactive Rate Adjustments

Report Number
2006-028C

We audited the costs invoiced by a contractor for retroactive rate adjustments and determined the adjustments were overstated by about $12,000 due to miscellaneous billing errors. The contractor agreed with our findings. Summary Only

Audit

TVA's Contracting Process

Report Number
2006-002C

We reviewed TVA's contracting process and noted several areas where improvements could result in better contract management and greater contractor compliance with commercial terms and conditions. Although we noted many instances of good practices being performed by various individuals in Procurement and TVA's Strategic Business Units, these practices were not universal.

Audit

Welding Services

Report Number
2006-012C

We audited $3.2 million of costs billed to TVA by a contractor for welding services performed at Browns Ferry and Sequoyah Nuclear Plants by one of its subcontractors and determined TVA had been billed $450,165 for unsupported and ineligible costs. The overbilling included (1) per diem payments that exceeded limitations or were ineligible under the contract, (2) ineligible mobilization/demobilization and travel expenses, (3) unsupported small tools and consumable costs, (4) labor costs that were either unsupported or billed at incorrect rates, and (5) unsupported subcontractor costs.

Audit

Fuel Fabrication Services

Report Number
2006-001C-03

We audited $32.7 million of costs billed to TVA by a contractor providing reload fuel fabrication services for Browns Ferry Nuclear Plant and determined TVA had been overbilled $5,545 due to the contractor's use of overstated hours and incorrect labor rates. Additionally, the contract did not have a formal authorization process for certain services to be performed by the contractor and the contractor could not provide documentation of TVA's authorization for some of the services it had billed TVA. The contractor agreed to credit TVA for the overbilled amount.

Audit

Nuclear Security Overtime

Report Number
2006-005C-02

We determined a TVA contractor providing nuclear security services was incurring a high level of overtime due to work schedules and headcount limitations. The headcount limitations had resulted in TVA paying $1.84 million in extra labor costs during 2004 and 2005. We estimated if the trend continued TVA would pay an extra $3.5 million over the planned three-year remaining term of the contract. TVA management stated they had reviewed the contractor's staffing levels and determined additional full-time positions were needed to man the security posts.

Audit

TVA's Prescription Safety Eyewear Program

Report Number
2006-511I

At the request of TVA Occupational Health and Workers' Compensation, we performed a limited scope review to assess whether policies, procedures, and key control activities ensure compliance with TVA's Prescription Safety Eyewear Program requirements. In summary, we determined TVA's policies and procedures adequately address the eligibility requirements and process to be followed in order to obtain prescription safety eyewear.

Audit

Gallatin Fossil Plant Coal Deliveries

Report Number
2006-524I

We compared Gallatin Fossil Plant (GAF) coal receipts using TVA and terminal shipment weights to identify whether any significant variances exist. Our review covered December 1, 2005, to May 3, 2006. We determined (1) coal receipt information input into FuelWorx (FWX) and the Daily Coal Report (DCR) were generally accurate and (2) significant variances exist between vendor/terminal invoiced weights and TVA delivered weights. Specifically:All but 1 of the 64 tested coal shipments were input into FWX and the DCR accurately.

Audit

Craft Labor Time Reporting (Browns Ferry Nuclear Plant Unit 1 Restart)

Report Number
2006-514I

At the request of TVA Nuclear (TVAN), we reviewed Stone and Webster Engineering Corporations' (SWEC) craft labor time reporting associated with the October 2005 Unit 1 Restart craft labor switch to five eight-hour straight-time work schedules. In 2005, TVA and the Tennessee Valley Trades and Labor Council modified their memorandum of understanding, including Attachment A, Mandatory ? Eight/Ten Straight-Time Attendance Agreement (LRS-54). The change was made to increase productivity (e.g., to curtail absenteeism and tardiness).

Audit