U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Https

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

All Reports

Peer Review of Dike C Buttressing

Report Number
2009-12910-02

TVA OIG retained Marshall Miller & Associates, Inc. (Marshall Miller) to conduct a peer review of the Stantec Consulting Services, Inc. (Stantec) stability calculations and construction documents for the Dike C Buttress at the Kingston Fossil Plant (Kingston). Dike C refers to the remaining section of the Kingston coal ash containment that did not fail in the December 22, 2008, spill. It is Marshall Miller's opinion that the planned Dike C Buttress produces stability enhancements that are sufficient based on Stantec's drained slope stability analyses.

Audit

Review of TVA's Kingston Ash Spill and Recovery Efforts

Report Number
2010-13034

As part of the Office of the Inspector General's (OIG) ongoing commitment to provide oversight in this area, we assessed Tennessee Valley Authority's (TVA) Kingston ash spill clean-up and recovery efforts. We assessed TVA's progress in two areas: (1) the clean-up of the ash and returning the area to its previous condition and (2) reparations to victims and restoration of the community.We found comprehensive efforts have been completed and are still ongoing pertaining to the clean-up of the spill.

Audit

Review of TVA's Plans for Offsite Transportation and Disposal of Ash from Kingston

Report Number
2008-12283-08

Marshall Miller & Associates, Inc. (Marshall Miller) was engaged by the Tennessee Valley Authority (TVA) Office of Inspector General to review the Transportation and Disposal Plans prepared by the Tennessee Valley Authority (TVA) in response to the ash release that occurred on December 22, 2008 at its Kingston Fossil Plant (KIF). Specifically, Marshall Miller was asked to determine if appropriate steps are being taken to minimize the environmental impacts and if regulatory requirements are being met.

Audit

Review of the Long Term Environmental Recovery Plan for Kingston

Report Number
2008-12283-06

Marshall Miller & Associates, Inc. (Marshall Miller) was engaged by the Tennessee Valley Authority (TVA) Office of Inspector General to review the adequacy and completeness of environmental recovery plans prepared by TVA in response to the ash spill that occurred on December 22, 2008, at the Kingston Fossil Plant (KIF). Generally, Marshall Miller found no significant deficiencies in any of the proposed alternatives for the restoration of the Swan Pond Embayment, including the selected alternative.

Audit

Inspector General Criminal Investigator Academy

Report Number
2009-12915

The Inspector General (IG) Criminal Investigator Academy (IG Academy) was officially established in February 1994 by a Memorandum of Understanding between the Federal Law Enforcement Training Center (FLETC) and the President's Council on Integrity and Efficiency (PCIE). The training academy is located at FLETC in Glynco, Georgia. The PCIE was superseded by the Council of the Inspectors General on Integrity and Efficiency (CIGIE) under the Inspector General Reform Act of 2008. Therefore, CIGIE assumed accountability for the IG Academy.

Audit

Review of Recreational Land Transactions

Report Number
2009-12728

Since 1933, Tennessee Valley Authority's (TVA) dam and reservoir construction program has acquired approximately 1.3 million acres of land for the creation of 34 reservoirs in five of the seven states in the Tennessee Valley region. Water flooded approximately 470,000 acres as part of the construction and operation of the reservoir system.

Audit

Distributor Review of Lenoir City Utilities Board

Report Number
2009-12594

OIG reviewed the Lenoir City Utilities Board (LCUB), a distributor for TVA power based in Lenoir City, Tennessee. LCUB also operates nonelectric businesses that include gas, water, and sewer utilities.

Audit

Review of Contractor's Management of Subcontractors

Report Number
2009-12916

We reviewed the design of a TVA contractor's process for administering subcontracted work for the Watts Bar Nuclear Plant Unit 2 construction project. Specifically, we reviewed the contractor's (1) invoice review process, (2) process for scheduling work, and (3) process for ensuring subcontractor work meets the contractor's specifications. In addition, we made inquiries regarding concerns raised about the management of measuring and testing equipment (M&TE).

Audit

Distributor Review of Scottsboro Electric Power Board

Report Number
2009-12510

The OIG performed a review of the City of Scottsboro Electric Power Board (Scottsboro) which is a distributor for TVA power based in Scottsboro, Alabama. Scottsboro also operates a telecommunications department that offers cable, internet, and telephone services. Also, Scottsboro is one of four distributors to which TVA granted retail rate setting authority. In 2002, TVA Board of Directors approved and made available to distributors six wholesale power contract flexibility options.

Audit

Contract for Quality Control Inspections and Nondestructive Examinations

Report Number
2009-12349

As part of our annual audit plan, we audited $35.07 million in costs billed to TVA by a contractor for providing quality control inspections and nondestructive examinations under two contracts. In summary, we found TVA had been overbilled $159,662 under one of the contracts, including (1) $136,030 in overstated payroll taxes, insurance, and related performance fees, (2) $18,228 in ineligible labor costs, and (3) $5,404 in duplicate fees. The contractor agreed with our findings and plans to reimburse TVA for the overbilled costs. Summary Only

Audit