Hartford Steam Boiler
We audited $10.4 million in costs billed to the Tennessee Valley Authority (TVA) by Hartford Steam Boiler Inspection and Insurance Company of Connecticut for nuclear Authorized Inspection Agency service under several contracts. The $10.4 million billed included (1) $4.8 million billed between October 1, 2001 and December 31, 2008 under one contract; (2) $4.1 million billed between December 1, 2007 and August 19, 2011, under second contract; and (3) $1.5 million billed between January 1, 2009, and July 22, 2011, under a third contract.