TVA’s Strategic Fiber Program
Report Information
Recommendations
We recommend the Vice President, Transmission System Projects, continue implementation of lessons learned identified from the Strategic Fiber Initiative program for application on future programs.
We recommend the Vice President, Transmission System Projects, for future programs, ensure estimated program costs are adequately supported, including the identification and evaluation of assumptions used to support the estimate.
We recommend the Vice President, Transmission System Projects, evaluate opportunities for maximizing surplus fiber revenue to help offset program costs.