Fort Loudoun Hydro Unit Two Hydro Life Extension Project
Report Information
Recommendations
We recommend the Vice President, Generation Projects and Outage Management, reinforce comprehensive cost tracking to ensure appropriate cost control.
We recommend the Vice President, Generation Projects and Outage Management, evaluate and determine if TVA can recover additional costs due to rework implications.
We recommend the Vice President, Generation Projects and Outage Management, take timely action to address contractor performance issues in accordance with the contract on future hydro unit repairs.
We recommend the Vice President, Generation Projects and Outage Management, continue with document repository implementation and take action to develop and implement a formal PM turnover process.