Description
We determined TVA was overbilled $56,023 (out of $5.3 million that had been billed) for services performed at BFN Unit 1 by a subcontractor. The overbilling occurred because the subcontractor used a craft labor classification that was not provided for by its subcontract. We also determined the subcontractor had not adjusted its workers compensation insurance costs to actual for the premium years ended July 1, 2003, and July 1, 2004, although its subcontract agreement required it. TVA is assessing our recommendations. Summary Only
Joint Report
Yes
Participating OIG
Tennessee Valley Authority OIG
Agency Wide
Yes (agency-wide)
Questioned Costs
$0
Funds for Better Use
$0