Date Issued
Report Number
2004-003C-02
Report Type
Audit
Description
We reviewed $109.8 million in costs paid by TVA to a contractor for providing engineering services associated with the restart of Browns Ferry Nuclear Plant (BFN) Unit 1. We questioned $2.5 million, including (1) the contractor's inclusion of the labor costs of its affiliate company in its performance base and (2) overcharges for labor and related costs and other direct costs. TVA decided to (1) allow the contractor to include the labor cost of its affiliate in its performance fee base and (2) recover any remaining costs that were not directly billable under the contract. Summary Only
Joint Report
Yes
Participating OIG
Tennessee Valley Authority OIG
Agency Wide
Yes (agency-wide)
Questioned Costs
$0
Funds for Better Use
$0