We reviewed $104.4 million in costs paid by TVA to a contractor for providing construction services for the restart of BFN Unit 1. We found the contractor overbilled TVA $1.5 million due to (1) the use of a craft labor category, incentive fee, and safety awards not provided for by the contract, (2) wrong indirect cost markups and unsupported labor costs, and (3) other miscellaneous overbillings. Additionally, we estimated TVA would save $995,000 by disallowing the use of an unauthorized labor classification. TVA subsequently decided to disallow $1,087,914 of the questioned costs and to discontinue use of the labor classification. Summary Only