Date Issued
Report Number
2012-14510
Report Type
Audit
Description
At the request of Tennessee Valley Authority's (TVA) Supply Chain, we audited AREVA NP, Inc.'s calendar year 2011 rate adjustments required under the terms in its contract. The contract provided for AREVA to complete engineering, licensing, construction, and startup operations of a single Bellefonte Nuclear Plant unit by the end of 2017. The objective of our audit was to determine if AREVA's rate adjustments were in accordance with the contract terms.In summary, we determined AREVA's net credit adjustment of $134,544 due to TVA was understated. Based on the methodology included in the contract, we determined the adjustment should be a credit to TVA of $564,765. AREVA officials agreed with our findings. AREVA issued TVA a credit of $375,875 and plans to issue TVA a credit for the remaining $188,890. Summary Only
Joint Report
Yes
Participating OIG
Tennessee Valley Authority OIG
Agency Wide
Yes (agency-wide)
Questioned Costs
$0
Funds for Better Use
$0